Grid impact studies and grid code compliance for renewable energy sources

Over the past 10 years NEPCO has carried out a series of auctions to develop renewable energy projects in Jordan. CESI was hired by several project developers to analyse the impact of new PV solar and wind power plants on the reliability and operation of the Jordanian power system, and to provide recommendations for how they could meet NEPCO’s requirements on the security, reliability, operational integrity and efficiency of the power system. 

The objectives of the project were to:

  • Confirm that any proposed new power plant was compliant with applicable NEPCO reliability standards
  • Confirm that the NEPCO transmission system could cope with the maximum power production of the project
  • Assess the impact of the proposed project on the reliability of the existing power system and transmission network, considering:
    • Thermal Impact
    • Voltage Impact
    • Short Circuit Impact
    • Power Quality Impact
  • Evaluate options to eliminate adverse reliability impacts resulting from the integration of renewable generation

Info
YEAR
2010-2017
Country
Jordan
Projects

Worldwide Projects

Operating strategy for CASA 1000 project
Under a USAID-supported project, CESI is helping the CASA-1000 Secretariat to identify the best way to operate the CASA-1000 Interconnector,…
Country
Afghanistan, Pakistan, Tajikistan
Services
Operational studies
Industries Expertise
HVDC Infrastructures
Project implementation consultancy for Advanced Metering Infrastructure for IESCO
The government of Pakistan has started a major programme, funded by the Asian Development Bank, to introduce advanced metering infrastructure…
Country
Pakistan
Services
Industries Expertise
Cost-benefit analysis for EuroAfrica project
CESI is performing the cost-benefit analysis of the 2,000MW HVDC submarine power interconnection that will connect Egypt to Europe via…
Country
Egypt, Greece
Services
Planning Studies
Industries Expertise
HVDC Infrastructures
Energy sector master plan for Kyrgyz Republic up to 2040
The Kyrgyz Republic is rapidly expanding its power sector and needs specific strategies, priorities and parameters to improve the sector’s…
Country
Kyrgyz Republic
Services
Planning Studies
Industries Expertise
Feasibility studies for the Mozambique-Zambia transmission line
Feasibility studies for the Mozambique-Zambia 400 kV Interconnector project The project, under the aegis of the Southern Africa Power Pool…
Country
Mozambique, Zambia
Services
Planning Studies
Industries Expertise
HVAC Infrastructures